Before we get to financing, we need to understand the tax system TIF is built on.
Start here: how property taxes work
Every property in a jurisdiction has an assessed value. The government applies a tax rate to that value and collects revenue.
What exactly is the “increment”?
Revenue continues to flow to schools, city, and county at the original assessed value — as if development never happened.
Additional revenue above the base, generated by rising assessed values, is captured by the TIF authority to service bond debt.
The frozen base is what the neighborhood was worth before. The increment is what it’s worth because of the investment. TIF redirects that new value toward paying off the investment that created it.
Simulation: the increment over time
The chart shows annual tax revenue in dollars — what each party actually collects each year. Move any slider and the chart updates immediately.
This is the district’s assessed value on the day the TIF was created. It never changes on this chart. Schools, the city, and the county keep collecting taxes on this amount every single year — the TIF does not touch it.
As property values grow above the frozen base, the extra tax revenue is the increment. The TIF authority captures it to pay off the bonds. Taxing districts receive none of this money until the TIF expires at year 10.
Once the TIF expires, the full assessed value — base plus all growth — flows to every taxing district. The purple area is what schools and the city were waiting for. A steeper growth rate makes this payoff much larger.
Base value shifts the whole chart up — a larger district generates more revenue even at the same rate. Growth rate steepens the slope; higher growth means a larger green increment and a bigger purple payoff for schools. Tax rate (mills) scales every bar proportionally — doubling the rate doubles the revenue for all three parties simultaneously.
The increment is the revenue stream. Financing is how you borrow against it before the money exists.
The six-step TIF process
The “but for” test — the hinge of the whole argument
Simulation: debt service risk
This is what the city assumed when it issued the bonds — a steady growth path for property tax revenue above the frozen base. The bond terms were set based on this projection. If actual growth matches it, there is no problem.
This is how much increment the district actually generates each year. When it falls below the debt service line, the TIF cannot cover its own bond payments. The gap between projected and actual is where TIF deals go wrong — and it is usually not discovered until the bonds are already issued.
The flat coral line is the annual debt service — the fixed amount the city must pay every year to service the bond, regardless of how much increment arrives. The coral bars show the shortfall: how much of that payment is not covered by the actual increment. Someone still has to pay — usually the general fund.
Bond amount and interest rate together set the flat debt service line — a bigger or costlier bond raises the hurdle every bar must clear. Projected growth shows what was promised; actual growth shows what happens. The scenario buttons jump to three canonical cases: Optimistic (growth nearly meets projections), Realistic (a modest gap), and Stressed (actual growth far below projections, sustained shortfall).
A successful TIF genuinely adds development that would not have occurred — and its increment covers the bond.
Case study: Millennium Park, Chicago
Grant Park rail yard prior to redevelopment
Millennium Park, City of Chicago
A contaminated rail yard becomes a $2.3 billion civic asset
The area north of the Loop was abandoned rail infrastructure on public land. No private developer was touching it. The city used TIF to fund infrastructure that made the site developable, then leveraged private philanthropy for the park itself. Surrounding property values exploded.
The same tool that revitalizes a brownfield can become a slush fund, a school defunding mechanism, or a debt trap.
Chicago: TIF as a shadow budget
Source: TIF Illumination Project, 2011
Detroit: when the increment never materializes
Source: Detroit Blight Removal Task Force / New York Times, 2014
Detroit illustrates a different failure mode: TIF districts in deeply distressed areas where population loss meant the increment simply never grew.
Source: Macerich/Fashion District Philadelphia developer rendering, c. 2015
The city controller challenged the “but for” before the ink dried
$55M TIF proposed for The Gallery renovation. Philadelphia’s own Controller questioned whether Macerich — a major S&P 500 REIT — actually needed a public subsidy in an improving retail market. The project proceeded. The “but for” was never independently verified.
Why TIF fails: the structural reasons
TIF is authorized in 49 states. It’s not going away. The question is how to use it responsibly.
The honest balance sheet
- Catalyzes genuinely distressed areas that private capital ignores
- Revenue-neutral in theory — only new growth is captured
- Aligns incentives: the city profits only if development succeeds
- Flexible tool adaptable to local needs and market conditions
- Off-balance-sheet financing that doesn’t require a referendum
- Diverts school district revenue for 20–35 years
- “But for” is fundamentally unverifiable — information asymmetry favors developers
- Often used in prosperous areas that didn’t need a subsidy
- Optimistic projections create long-term debt liability
- Opaque — outside normal democratic budget oversight
- Shifts development, doesn’t create it