Capital Fund
Planning
City Transit Authority Capital Improvement Program
The City Transit Authority (CTA) operates one of the region's largest public transit systems — serving over 1 million daily riders across rail, subway, light rail, and bus networks. In FY2025, the CTA's board approved a $922.8 million annual capital budget, part of an all-time-high $14 billion 12-year Capital Program enabled by the federal Infrastructure Investment and Jobs Act (IIJA).
In this exercise you play the role of a capital budget analyst at the City Transit Authority (CTA). The board has approved a 5-year, $1.575 billion Capital Improvement Plan (FY2025–FY2029). Your job is to build the financial architecture behind that plan: scheduling project expenditures, mapping out funding sources, modeling bond debt service, and assessing the impact on the authority's operating budget.
Four Tasks in This Exercise
- Task 1 — CIP Schedule: Build the project-by-year spending matrix and compute annual totals.
- Task 2 — Funding Sources: Allocate federal, state, and local financing for each year.
- Task 3 — Debt Service: Construct a 20-year bond amortization schedule for the local share.
- Task 4 — Operating Impact: Calculate debt service as a percentage of the growing operating budget.
Download the Excel Starter file above. The workbook contains four worksheets — one per task. Pre-filled data is provided in each sheet; your job is to enter the formulas indicated by the column headers.
CIP Annual Schedule
PendingThe CIP organizes capital spending by project category (rows) and fiscal year (columns). Your first task is to calculate the totals that summarize this matrix — both across projects for each year and across years for each project.
What is a Capital Improvement Plan?
A Capital Improvement Plan (CIP) is a multi-year schedule that identifies needed capital projects, estimates their costs, and aligns them with projected funding. Transit agencies use CIPs to:
- Communicate investment priorities to elected boards and the public
- Sequence projects to match funding availability (especially federal grant timelines)
- Satisfy federal requirements for State of Good Repair tracking
Step-by-Step
=SUM(B3:F3) to total the MFL Railcar Replacement project across all five years.=SUM(B3:B10) to total all FY2025 capital spending across projects.Capital Spending by Category — FY2025 to FY2029
Hints
=SUM(B3:F3) dragged down. Row 11: =SUM(B3:B10) dragged right. Grand total G11: =SUM(G3:G10).Paste three values from your Excel sheet:
| Project | FY2025 | FY2026 | FY2027 | FY2028 | FY2029 | 5-Yr Total |
|---|---|---|---|---|---|---|
| MFL Railcar Replacement | $85,000,000 | $95,000,000 | $120,000,000 | $110,000,000 | $70,000,000 | $480,000,000 |
| Trolley Modernization | $30,000,000 | $45,000,000 | $65,000,000 | $85,000,000 | $95,000,000 | $320,000,000 |
| Station Rehabilitation | $38,000,000 | $42,000,000 | $48,000,000 | $45,000,000 | $42,000,000 | $215,000,000 |
| Track & Infrastructure | $35,000,000 | $37,000,000 | $38,000,000 | $38,000,000 | $37,000,000 | $185,000,000 |
| Bus Fleet Replacement | $28,000,000 | $32,000,000 | $30,000,000 | $28,000,000 | $27,000,000 | $145,000,000 |
| Technology & Systems | $15,000,000 | $18,000,000 | $22,000,000 | $20,000,000 | $20,000,000 | $95,000,000 |
| Facilities & Maintenance | $12,000,000 | $14,000,000 | $16,000,000 | $17,000,000 | $16,000,000 | $75,000,000 |
| ADA Accessibility | $10,000,000 | $12,000,000 | $13,000,000 | $13,000,000 | $12,000,000 | $60,000,000 |
| Annual Total | $253,000,000 | $295,000,000 | $352,000,000 | $356,000,000 | $319,000,000 | $1,575,000,000 |
Funding Source Allocation
PendingCapital projects are rarely funded from a single source. Transit agencies blend federal formula grants, competitive federal discretionary grants, state assistance, and locally-raised bond proceeds. For each fiscal year, you will calculate how much comes from each source — and determine the local share that must be bond-financed.
Funding Source Rules for This Exercise
- Federal Formula Funds (FTA §5307/§5337): 40% of annual capital need. These are formula-based allocations received annually based on ridership and route miles.
- PA State Capital Assistance (Act 89): 20% of annual capital need. Pennsylvania's dedicated transit capital funding stream.
- Federal Discretionary Grants (IIJA): Lump-sum competitive grants — $80M awarded in FY2025 (MFL railcar contract), $45M in FY2027 (trolley signal system). These are given; do not calculate.
- Local Bond Financing: The remainder after all other sources. This is what the authority must borrow.
Step-by-Step
=B4*0.40 for the Federal Formula amount. Drag right through F5, then enter =SUM(B5:F5) in G5.=B4*0.20 for State Assistance. Drag right, then sum in G6.=B4-B5-B6-B7 for Local Bonds. Drag right; in G8 enter =SUM(B8:F8). This should total $505,000,000.=SUM(B5:B8). It should equal B4 exactly. If not, recheck your formulas.=(B5+B7)/B8. Drag right through FY2029. Note the FY2025 ratio.Annual Capital Funding by Source — FY2025 to FY2029
Hints
=B4*0.40. Row 6 (State): =B4*0.20. Row 8 (Local Bonds): =B4-B5-B6-B7. Leverage ratio: =(B5+B7)/B8. Drag all formulas right through column F.Paste three values from your Funding_Sources sheet:
| Source | FY2025 | FY2026 | FY2027 | FY2028 | FY2029 | Total |
|---|---|---|---|---|---|---|
| Annual Capital Need | $253,000,000 | $295,000,000 | $352,000,000 | $356,000,000 | $319,000,000 | $1,575,000,000 |
| Federal Formula (40%) | $101,200,000 | $118,000,000 | $140,800,000 | $142,400,000 | $127,600,000 | $630,000,000 |
| State Act 89 (20%) | $50,600,000 | $59,000,000 | $70,400,000 | $71,200,000 | $63,800,000 | $315,000,000 |
| Federal Discretionary (given) | $80,000,000 | $0 | $45,000,000 | $0 | $0 | $125,000,000 |
| Local Bond Financing | $21,200,000 | $118,000,000 | $95,800,000 | $142,400,000 | $127,600,000 | $505,000,000 |
| Federal Leverage Ratio | 8.55x | 1.00x | 1.94x | 1.00x | 1.00x | — |
Bond Debt Service Schedule
PendingThe authority will issue $505,000,000 in revenue bonds to cover the 5-year local share identified in Task 2. These bonds carry a 4.50% annual interest rate and a 20-year term, with equal annual debt service payments (level annuity). Your task is to build the complete 20-year amortization schedule.
How Bond Amortization Works
Each year the authority makes a fixed annual payment that covers both interest and principal. In early years, most of the payment is interest (because the outstanding balance is high). Over time, as the balance falls, less interest accrues and more of each payment retires principal — even though the total payment stays the same.
- Interest portion: Outstanding balance × annual rate
- Principal portion: Fixed payment − interest
- Ending balance: Beginning balance − principal repaid
Step-by-Step
=ABS(PMT(C3,D3,-B3)). This is the fixed annual payment — approximately $38,822,453.=B3 (the full bond amount as the Year 1 beginning balance). In B7 through B25, enter =F6, =F7, etc. (the prior year's ending balance).=$E$3 (absolute reference to the annual payment). Drag down through C25.=B6*$C$3 (interest = balance × rate). Drag down through D25.=C6-D6 (principal = payment − interest). In F6, enter =B6-E6 (ending balance). Drag both down through row 25.20-Year Debt Service: Interest vs. Principal Breakdown
Hints
=ABS(PMT(C3,D3,-B3)). Year 1 beginning = bond amount. Year 2+ beginning = prior ending (=F6 dragged down). Interest: =B6*$C$3. Principal: =C6-D6. Ending: =B6-E6.Paste three values from your Debt_Service sheet:
Schedule Preview (Years 1–5 and 18–20)
| Year | Beginning Balance | Annual Payment | Interest | Principal | Ending Balance |
|---|---|---|---|---|---|
| 2025 (Yr 1) | $505,000,000 | $38,822,453 | $22,725,000 | $16,097,453 | $488,902,547 |
| 2026 (Yr 2) | $488,902,547 | $38,822,453 | $22,000,615 | $16,821,838 | $472,080,709 |
| 2027 (Yr 3) | $472,080,709 | $38,822,453 | $21,243,632 | $17,578,821 | $454,501,888 |
| 2029 (Yr 5) | $436,132,020 | $38,822,453 | $19,625,941 | $19,196,512 | $416,935,508 |
| 2034 (Yr 10) | $307,191,129 | $38,822,453 | $13,823,601 | $24,998,852 | $282,192,277 |
| 2042 (Yr 18) | $106,721,539 | $38,822,453 | $4,802,469 | $34,019,984 | $72,701,556 |
| 2043 (Yr 19) | $72,701,556 | $38,822,453 | $3,271,570 | $35,550,883 | $37,150,673 |
| 2044 (Yr 20) | $37,150,673 | $38,822,453 | $1,671,780 | $37,150,673 | $0 |
Total debt service over 20 years: $776,449,060 • Total interest paid: $271,449,060 • Total principal: $505,000,000
Operating Budget Impact
PendingBond debt service is not a capital expense — it is an operating expense paid from the authority's annual operating budget. Understanding how debt service grows relative to the operating budget is critical for long-range fiscal health. In this task you model the debt service burden over the first five years of the CIP.
Key Parameters for Task 4
- FY2025 Operating Budget: $1,740,000,000 (CTA FY2025 approved budget)
- Annual Budget Growth Rate: 3.0% per year (driven by labor contracts, fuel, and maintenance inflation)
- Annual Debt Service: $38,822,453 (from Task 3 — fixed for the full 20-year term)
Step-by-Step
=B4*1.03. Drag right through F4 to calculate FY2026–FY2029 operating budgets.=B5/B4*100 to calculate the debt service ratio as a percentage. Drag right through F6.Operating Budget vs. Debt Service Ratio — FY2025 to FY2029
Hints
=B4*1.03 dragged right. DS ratio: =B5/B4*100 dragged right. FY2025 ≈ 2.23%, declining to ≈ 1.98% by FY2029.Paste three values from your Operating_Impact sheet:
| FY2025 | FY2026 | FY2027 | FY2028 | FY2029 | |
|---|---|---|---|---|---|
| Operating Budget | $1,740,000,000 | $1,792,200,000 | $1,845,966,000 | $1,901,344,980 | $1,958,385,329 |
| Annual Debt Service | $38,822,453 | $38,822,453 | $38,822,453 | $38,822,453 | $38,822,453 |
| DS as % of Operating | 2.23% | 2.17% | 2.10% | 2.04% | 1.98% |
Analysis & Policy Questions
Use your completed spreadsheet and the data from the four tasks to address the following questions. These are designed for written response or in-class discussion.
In FY2025, the federal leverage ratio is 8.55x — meaning the authority attracts $8.55 in federal dollars for every $1 of local bond financing. In FY2026 and later years without discretionary grants, the ratio falls to approximately 1.0x.
Questions to consider:
- What accounts for this dramatic variation in leverage across years?
- If a large discretionary grant is awarded in Year 1 but the project takes three years to build, how does grant timing affect cash flow and fund balance management?
- What risks does an authority face if it builds a capital plan that depends heavily on competitive federal grants that may or may not be awarded?
- How should a capital plan treat uncertain discretionary grants — as committed funding or as a contingency?
The authority issued 20-year bonds to finance a mix of assets with very different lifespans:
- Railcars: 30–40 year useful life
- Track & Infrastructure: 30–50 years
- Bus Fleet: 12–15 years
- Technology & Systems: 5–10 years
Questions to consider:
- For which projects does a 20-year bond term make sense? For which is it too long or too short?
- What problems arise when you finance a 10-year asset with a 20-year bond? What about financing a 40-year asset with a 10-year bond?
- How might rating agencies or bond covenants constrain the term of financing for short-lived assets?
The debt service-to-operating-budget ratio ranges from 2.23% in FY2025 to 1.98% in FY2029. Transit bond rating agencies typically flag affordability concerns when this ratio exceeds 10–15%.
Questions to consider:
- On its face, the CTA's position appears comfortable. What assumptions in your model are most critical to this conclusion?
- The CTA already carries significant legacy debt from prior capital programs. How would you incorporate existing debt service obligations into this analysis?
- If the operating budget growth rate slowed from 3% to 1% (e.g., due to a recession), how would the DS ratio change by FY2029? Recalculate and compare.
- What non-financial factors (political pressure, labor contracts, federal compliance requirements) might constrain the authority's ability to manage its debt burden?
Pennsylvania's Act 89 capital assistance is funded partly by liquid fuels tax revenues, which have been declining as electric vehicles displace gasoline-powered cars.
Scenario: Suppose Act 89 capital assistance is reduced from 20% to 15% of annual capital needs for FY2027–FY2029.
- How much additional local bond financing would be required for each affected year?
- What would the new total bond amount be? Recalculate the annual debt service using the PMT function.
- How much additional interest would the authority pay over the full 20-year life of the expanded bond issue?
- At what point does a state funding cut become a structural threat to capital program delivery?
Major capital projects — new railcars on the Market-Frankford Line, trolley modernization — primarily benefit riders on specific corridors. Yet bond debt service is repaid from system-wide revenues: fares paid by all riders, state subsidies, and local government contributions.
Questions to consider:
- Is it equitable for riders on unaffected routes to help pay for improvements they will not directly use?
- How does the geographic and demographic distribution of the CTA's ridership affect the equity implications of this capital plan?
- What alternatives exist — dedicated revenue bonds, TIF districts, special assessment districts — that might better align who pays with who benefits?
- How should public transit agencies balance system-wide equity goals with the need to invest heavily in the most-used (and often most-underserved) corridors?